Hatis Secondary school after V. Vardanyan SNCO

Capacity

20,5 kW

Location

Hatis Secondary school after V. Vardanyan SNCO

Solar modules

SOLET 410MH5-54 50 pcs

Inverter

Solax X3-PRO-20K-G2 1 pcs 20 kW

Annual electricity production

30750 kWh

"Solar Farm" LLC, Gegharkunik Province, Shoghakat village 5000 kW
"Solar Farm" LLC, Gegharkunik Province, Shoghakat village
The installation of 6 MW pick power (5 MW nominal power ) plant was made with 100 blocks (inverters). The Power plant is equipped with accident-prevention systems to avoid short circuit, non-sinusoidal currents, overvoltages, abrupt voltage changes, zero wire breakage problems, and other failures. In the surrounding area was installed an earth ground loop with a resistance less than 4 ohms for AC and DC circuits.
07 Nov 2020
5000 kW
SECONDARY SCHOOL OF SARATAK 30,34 kW
SECONDARY SCHOOL OF SARATAK
30,34 kW
Ani Resort" Hankavan, Kotayk province 𝟏𝟑𝟎․𝟗 kWt
Ani Resort" Hankavan, Kotayk province
This innovative solar plant installed to save nature and save electricity costs
𝟏𝟑𝟎․𝟗 kWt
"EDMET" LLC, Yerevan, Shengavit administrative district 114 kW
"EDMET" LLC, Yerevan, Shengavit administrative district
114 kW